Beardwell Construction upgrades electrics at Essex Police's Grays station
- 7 Force Strategic Collaboration
- East of England
- Call-off from a framework agreement
- 9 February 2026 to 4 September 2026
7 Force Strategic Collaboration hired Beardwell Construction to upgrade the electrical infrastructure at Grays Police Station for Essex Police.
Beyond the electrics, the car park was to be resurfaced. Other work covered fire alarms and emergency lighting in custody, plus suspended ceilings and corridor lighting.
The firm is a small business, and the £1.4m contract was let as a call-off from a framework. It ran from February 2026 and was due to end in September 2026.
- What
- Electrical installation, rewiring and repairs
- Supplier
- Beardwell Construction Ltd
- Value
- £1.44m
- How it was bought
- Call-off from a framework agreement
- Dates and next
- Feb 2026 to Sep 2026