ICU heat pump compressors for Airedale come from Mitsubishi Electric
- Airedale NHS Foundation Trust
- Yorkshire and the Humber
- Direct award
- 1 November 2026 to 31 March 2027
Airedale NHS Foundation Trust is buying replacement compressors from Mitsubishi Electric Europe for the air source heat pumps at its modular intensive care unit. AGH Solutions Ltd, a wholly owned subsidiary of the trust, is placing the contract.
The pumps heat the unit for critically ill patients and are only about five years old, but the compressors have failed. The trust is not waiting for the cause to be settled, as new compressors take 8 to 10 weeks to arrive.
The trust awarded the £133,759 contract, excluding VAT, directly in October 2026. It is due to end in March 2027.
Contract ends March 2027
- What
- Heat pumps
- Supplier
- Mitsubishi Electric Europe
- Value
- £133,759
- How it was bought
- Direct award
- Dates and next
- Nov 2026 to Mar 2027