National Grid connects Aston University's new low-carbon Energy Centre
- Aston University
- West Midlands
- Below threshold - without competition
- 3 July 2026 to 31 March 2028
Aston University needs more electrical capacity for its new low-carbon Energy Centre, and National Grid is carrying out the connection works to secure it.
The connection belongs to the university's Heat Network Decarbonisation and Energy Efficiency Upgrades project, paid for by the Public Sector Decarbonisation Scheme. National Grid runs the local electricity distribution network, and because the works tie into it, no other firm could carry them out.
The university awarded the £90,120 contract directly, and it runs to March 2028.
Contract ends March 2028
- What
- Electricity network works and connections
- Buyer
- Aston University
- Supplier
- National Grid
- Value
- £90,120
- How it was bought
- Below threshold - without competition
- Dates and next
- Jul 2026 to Mar 2028