Bath Western Riverside planning work for B&NES goes to St William Homes
- Bath & North East Somerset Council
- South West
- Below threshold - without competition
- 3 August 2026 to 31 July 2029
Bath & North East Somerset Council has hired St William Homes LLP to seek planning permission on council-owned land at Bath Western Riverside.
The site is the former Bath gas works. The first phase of the scheme delivered 854 homes, 25% of them affordable. For the second phase, the council owns 31.5% of the site and St William Homes owns the other 68.5%. The council bought its share in 2019 to raise the number of affordable homes it could deliver. St William already has permission for its own part, and the application will cover residential blocks with supporting infrastructure.
The council awarded the work directly, without a competition, at £173,099. The contract runs from August 2026 to July 2029.
Contract ends July 2029
- What
- Planning consultancy for applications and appeals
- Supplier
- St William Homes LLP
- Value
- £173,099
- How it was bought
- Below threshold - without competition
- Dates and next
- Aug 2026 to Jul 2029