Habitat bank work on Barnsley Council land goes to Wildscapes
- Barnsley Metropolitan Borough Council
- Yorkshire and the Humber
- Open procedure, 10 bids
- 22 July 2026 to 21 July 2031
Barnsley Metropolitan Borough Council appointed Wildscapes as landscape manager of its habitat bank at £140,275, just over a third of the £380,000 estimate.
The habitat bank sits on council-owned land. Wildscapes carries out the planned work to create new habitats and improve existing ones. It then manages them for five years, the opening stretch of the 30 years over which the habitats are to be managed.
Ten firms bid in an open tender scored 55% on quality, 40% on price and 5% on social value. The council awarded the contract in May 2026, and it runs to July 2031.
Contract ends July 2031
- What
- Habitat creation and enhancement works
- Supplier
- Wildscapes
- Value
- £140,275
- How it was bought
- Open procedure
- 10 bids
- Dates and next