Keynsham Civic Centre gets green oak planters from Stringer Construct
- Bath & North East Somerset Council
- South West
- 23 February 2026 to 23 June 2026
Bath & North East Somerset Council hired Stringer Construct to replace the rotting timber planters at Keynsham Civic Centre with green oak.
Oak was picked so the planters would last and stand up to wear. The works also set out to make the planters safe and easy for any visitor to get around, with potential hazards kept to a minimum.
The work was estimated at £130,000, and the award in February 2026 was £175,494. The four-month contract was due to end in June 2026.
- What
- Park furniture
- Supplier
- Stringer Construct Ltd
- Value
- £175,494
- How it was bought
- Not published
- Dates and next
- Feb 2026 to Jun 2026