Lythwood Sports Complex pavilion works go to Shuker Building
- Bayston Hill Parish Council
- Open procedure, 5 bids
- 1 April 2027 to 1 October 2027
Bayston Hill Parish Council will pay Shuker Building & Development Limited £813,697 to extend and refurbish the pavilion at Lythwood Sports Complex. The figure is more than twice the £400,000 the council estimated when it went to tender.
The pavilion will gain changing rooms and an entrance with a plant room in single-storey extensions, and its interior will be refurbished. Outside, the car park will be extended, a storage building put up and more renewables fitted, alongside new landscaping.
Five firms bid in an open tender, and Shuker Building, a small business, won in October 2026. The works are due to finish in October 2027.
Contract ends October 2027
- What
- Building extensions, alterations and minor works
- Value
- £813,697
- How it was bought
- Open procedure
- 5 bids
- Dates and next
- Apr 2027 to Oct 2027