Avon Beach to Highcliffe groyne and beach works for BCP go to Earlcoate
- Bournemouth, Christchurch and Poole Council
- South West
- Restricted procedure
- 4 May 2026 to 31 July 2026
Bournemouth, Christchurch and Poole Council hired Earlcoate Construction & Plant Hire to shore up the groynes between Avon Beach and Highcliffe.
Rock armour on the existing groynes had shifted out of place. Earlcoate was to recover and restack it, with an allowance for new rock, raising and strengthening the groynes' heads and crests. Higher, stronger groynes were meant to hold more beach material in the cells between them. The work also included recycling beach material from Highcliffe to Avon Beach and Friars Cliff, plus repairs to groyne markers and minor maintenance.
Earlcoate was chosen through a further competition under a framework, and the £336,725 contract was awarded in April 2026. The three-month job was due to end in July 2026.
- What
- Coastal protection and sea defences
- Value
- £336,725
- How it was bought
- Restricted procedure
- Dates and next
- May 2026 to Jul 2026