Christchurch Quay wall repairs for BCP Council go to Suttle Projects
- Bournemouth, Christchurch and Poole Council
- South West
- RFQ
- 13 August 2026 to 31 December 2026
Bournemouth, Christchurch and Poole Council hired Suttle Projects, a small business, to repair the quay wall at Christchurch where it has been undermined.
The repairs are localised. Concrete bagwork is used to restore some of the support at the foot of the wall and to limit further washout. Suttle Projects also repairs coping stones and deals with the trip hazards that go with them.
The council asked for quotes. The work, estimated at £22,713, runs from August 2026 to December 2026.
Contract ends December 2026
- What
- Harbour, marine and mooring works
- Supplier
- Suttle Projects
- Value
- £22,713
- How it was bought
- RFQ
- Dates and next
- Aug 2026 to Dec 2026