City Quays 3 office fit-out for Belfast Harbour goes to Graham
- Belfast Harbour
- Northern Ireland
- Open, 3 bids
- 16 December 2025 to 1 May 2026
Belfast Harbour hired Graham to fit out floors 6, 5 and part of floor 4 at City Quays 3, a 16-storey office development. The work covered Category A and Category B fit-out across about 34,500 sq ft. It also called for new internal staircases between floors 4 and 5 and between floors 5 and 6, cut through the existing floor slabs.
Three bids came in, and price made up the whole score. The award was £7.75m, against an estimate of £6.6m. The contract started in December 2025 and was due to end in May 2026.
- What
- Interior fit-out and office reconfiguration
- Buyer
- Belfast Harbour
- Supplier
- GRAHAM
- Value
- £7.75m
- How it was bought
- Open
- 3 bids
- Dates and next