Evolt Charging to supply EV charging, solar and battery storage for Blaby
- Blaby District Council
- East Midlands
- RFQ
- 31 December 2026 to 30 December 2029
Blaby District Council has chosen Evolt Charging to put in EV charging infrastructure alongside solar generation and battery storage. The firm will also run and maintain everything it installs.
Blaby sought quotes rather than holding an open tender. The contract is estimated at £188,940. It is due to start in December 2026 and run for three years, with extensions that could take it to December 2032.
Contract ends December 2029
- What
- EV chargepoint installation and maintenance
- Supplier
- Evolt Charging
- Value
- £188,940
- How it was bought
- RFQ
- Dates and next
- Dec 2026 to Dec 2029
- Option to Dec 2032