Blackburn with Darwen Borough Council hired Bethell Construction for active travel improvements on Gorse Street and Lower Audley Street in Blackburn. The main element was an uncontrolled crossing for pedestrians, with a kerbed island in the middle.
The work also took in carriageway patching, new road markings, rebuilt footways and the removal of trees. Lighting columns were moved or replaced, with the electrical work that went with them.
The council chose Bethell after an open tender. The £344,454 contract was due to run from April to May 2026.