Minster Surfacing to resurface Central Park footpaths in Boston
- Boston Borough Council
- East Midlands
- Below threshold - open competition
- 4 January 2027 to 31 March 2027
Boston Borough Council has hired Minster Surfacing to repair and resurface the footpaths in Central Park and the Skatepark on Thorold Street, Boston. The council wants a finish that lasts and is safe, and the park will have to stay as open as possible while the work goes on.
Price counted for 75% of the score, with method statement and programme at 10% each and social value at 5%.
Minster Surfacing was awarded the work in November 2026 at £213,342, and it is due to finish by March 2027.
Contract ends March 2027
- What
- Hard landscaping and paths in parks and grounds
- Supplier
- Minster Surfacing Limited
- Value
- £213,342
- How it was bought
- Below threshold - open competition
- Dates and next
- Jan 2027 to Mar 2027