Upper Thurne pumping stations go to BAM Nuttall for the Broads IDB
- Broads (2006) Internal Drainage Board
- East of England
- Open, 3 bids
- 14 April 2026 to 10 September 2028
The Broads (2006) Internal Drainage Board hired BAM Nuttall to replace three drainage pumping stations at Martham, Potter Heigham and Brograve. The pumps keep the catchment from permanent flooding by clearing excess water off the marshes. BAM Nuttall designs and builds each new station near the old one and decommissions the old station.
The board can also add a fourth site, either Somerton South Pumping Station and Culvert or Repps pumping station. Its estimate was £8m to £12m for the first three sites, plus up to £6m for the fourth.
The Water Management Alliance (WMA) ran the open tender for the board, and three bids came in. Price counted for 50% of the score. BAM Nuttall won in March 2026 at £9,465,953. The contract can run to March 2029 if the fourth station needs more time.
Contract ends September 2028
- What
- Pumping stations and small treatment plants
- Supplier
- BAM Nuttall
- Value
- £9.47m
- How it was bought
- Open
- 3 bids
- Dates and next
- Apr 2026 to Sep 2028
- Being re-tendered now