Contract awardedModular and portable buildings

MTX Contracts rebuilds the Therapies building at Stoke Mandeville Hospital

Buckinghamshire Healthcare NHS Trust hired MTX Contracts to redevelop the Therapies building at Stoke Mandeville Hospital. The existing building is to be demolished and replaced using volumetric modular construction.

The work also covers design, groundworks, drainage and water connections, and clearing asbestos from the site.

MTX Contracts' was the only bid, and the trust awarded MTX £7.8m in March 2026.

What
Modular and portable buildings
Value
£7.82m
How it was bought
Not published
1 bid
Dates and next
2 Mar 2026

How it was bought

1 official notice
  1. 10 Mar 2026Award noticeFind a Tender

How it compares

With every modular and portable buildings award since 2021

Half of awards fall between £98,047 and £811,975Median £281,304

Awards
818
Firms that won them
286
Median award
£281,304
of 777 with a value
This award
Bigger than 95%
of them
Typical length
6 months
In South East
109 awards

MTX Contracts ranks 19th of 286 firms for modular and portable buildings awards since 2021.

RankFirmAwardsValue
1Locked155£164m
2Locked38£30.8m
3Locked24£206.3m
4Locked21£54.5m
5Locked18£16.5m
6Locked17£8.42m
19MTX Contracts Won this one6£13.3m
See who wins this work

Figures to 21 November 2026

Modular and portable buildings at other buyers

Buckinghamshire Healthcare NHS Trust has awarded 111 contracts since 2021.

See Buckinghamshire Healthcare NHS Trust's page
  • MTX Contracts has won 27 public contracts since 2021, 6 of them from Buckinghamshire Healthcare NHS Trust.

    • Aug 2026Locked£203,383
    • Mar 2026This purchase£7.82m
    • Jan 2026Locked£227,084
    • Oct 2025Locked£637,785
    • Sep 2025Locked£326,597
    • Jul 2025Locked£1.18m
    See the contracts

4 modular and portable buildings tenders are open now

See them
More modular and portable buildings contracts awarded in 2026