Financial planning solution: Cadent Gas plans a replacement
- Cadent Gas Limited
- West Midlands
- 1 March 2027 to 28 February 2030
Cadent Gas Limited plans to replace its financial planning solution and has asked the market what is on offer. It wants suppliers to give a rough order of magnitude cost.
Cadent asked for whole-life costs and likely timescales, as well as what each solution can do and the effort needed to implement it. It also asked about operating models and delivery approaches. Responses were due by 9 October 2026. Taking part does not tie Cadent to any supplier or to running a procurement.
Cadent has published no estimate. A contract would run for three years from March 2027.
- What
- Financial planning, budgeting and reporting software
- Buyer
- Cadent Gas Limited
- Estimated value
- Not published
- How it will be bought
- Not published
- Responses due
- 9 Oct 2026
- Contract dates
- Mar 2027 to Feb 2030