MATS Phase 2A junction works in March, Fenland, go to Geoffrey Osborne
- Cambridgeshire County Council
- East of England
- Call-off from a framework agreement
- 9 February 2026 to 8 February 2027
Cambridgeshire County Council hired Geoffrey Osborne to build two road schemes in March, Fenland, under the MATS programme. The programme tackles congestion and safety problems in the town.
At Twenty Foot Road, the works move the road 25m north of where it now meets the A141, making room for a new junction with traffic signals. At the St Peter's Road junction, High Street traffic gets a right-turn lane into St Peter's Road and the nearby controlled crossings are upgraded.
The Cambridgeshire and Peterborough Combined Authority's governing board approved both schemes for construction in July 2024. The council ordered the works through the Eastern Highways Alliance Framework 4 after a further competition. The £2m contract runs to February 2027.
Contract ends February 2027
- What
- Highway improvement and road safety schemes
- Supplier
- Geoffrey Osborne
- Value
- £2m
- How it was bought
- Call-off from a framework agreement
- Dates and next
- Feb 2026 to Feb 2027