Ovenden Allworks wins Canterbury's rebuild of East Quay Ballast Section 3
- Canterbury City Council
- South East
- Below threshold - limited competition, 3 bids
- 14 September 2026 to 31 March 2027
Ovenden Allworks Limited is rebuilding Section 3 of the East Quay Ballast in Whitstable for Canterbury City Council.
The structural engineering works restore the integrity of this part of the quay, and the scope stops at this one section. They call for marine construction experience and must meet harbour safety standards. The council expected the works to take 32 weeks.
The limited competition drew three bids. Ovenden Allworks won the £1,008,623 contract in May 2026, and the works are due to end in March 2027.
Contract ends March 2027
- What
- Harbour, marine and mooring works
- Supplier
- Ovenden Allworks Limited
- Value
- £1.01m
- How it was bought
- Below threshold - limited competition
- 3 bids
- Dates and next