Believ wins Central Bedfordshire's 15-year EV charge point concession
- Central Bedfordshire Council
- East of England
- Open procedure, 4 bids
- 1 November 2026 to 31 October 2041
Believ builds and operates public electric vehicle charge points across Central Bedfordshire under a 15-year concession for Central Bedfordshire Council.
The contract is LEVI Tender 1, one of two the council ran after it was allocated £1,413,000 from the Local Electric Vehicle Infrastructure (LEVI) fund. It covers 7-22kW charge points for residents, with at least 500 on streets and 200 in hubs such as car parks. Believ funds the network, backed by £1,298,000 of the council's LEVI grant. Bidders could not win both tenders.
Four firms bid, with technical quality worth 80% of the score, social value 10% and commercial 10%. The tender estimated the concession at £35m. Believ won in June 2026 at £42m, with the contract running to October 2041.
Contract ends October 2041
- What
- Public EV charging network concessions
- Supplier
- Believ
- Value
- £42m
- How it was bought
- Open procedure
- 4 bids
- Dates and next
- Nov 2026 to Oct 2041
- Option to Oct 2042