Renewable Dynamics assesses wind farm impacts for Central Bedfordshire
- Central Bedfordshire Council
- East of England
- Below threshold - without competition
- 22 July 2026 to 30 September 2026
Central Bedfordshire Council hired Renewable Dynamics Limited to assess how a proposed development could affect a wind farm. The firm looked at the economic impact as well as the effect on the turbines, using computational fluid dynamics (CFD) modelling. It was also to recommend how any harm could be reduced or compensated for.
The council awarded the £37,400 contract directly. It was due to end in September 2026, with an option to extend it to September 2027.
- What
- Independent technical advice and review
- Supplier
- Renewable Dynamics Limited
- Value
- £37,400
- How it was bought
- Below threshold - without competition
- Dates and next
- Jul 2026 to Sep 2026
- Option to Sep 2027