Northwich station refurbishment goes to MPH Construction
- Cheshire West and Chester Council
- North West
- Direct
- 1 April 2026 to 31 October 2026
Cheshire West and Chester Council awarded MPH Construction Ltd the refurbishment of Northwich railway station.
The contract took the project through RIBA stages 5 to 7. MPH Construction is a small business.
The council awarded the seven-month, £240,000 contract directly in December 2025, without a competition. The work was due to end in October 2026.
- What
- Building refurbishment, remodelling and conversion
- Supplier
- MPH Construction Ltd
- Value
- £240,000
- How it was bought
- Direct
- Dates and next
- Apr 2026 to Oct 2026
- Option to Dec 2026