Lorne Stewart installs a heat pump at Acre Mills Outpatients Building
- Calderdale and Huddersfield Solutions Ltd
- Yorkshire and the Humber
- Limited, 2 bids
- 1 July 2026 to 31 January 2027
Calderdale and Huddersfield Solutions Ltd (CHS) hired Lorne Stewart to install a heat pump at the Acre Mills Outpatients Building. The pump replaces all of the building's gas boilers as part of a decarbonisation project.
The contract also covers work on the front of Acre Mills, a building patients do not use, where the glazing is replaced and loft insulation fitted. The funding comes from Salix finance.
CHS received two bids, and Lorne Stewart's was chosen. The £412,640 contract runs from July 2026 to January 2027.
Contract ends January 2027
- What
- Heat pumps
- Supplier
- Lorne Stewart
- Value
- £412,640
- How it was bought
- Limited
- 2 bids
- Dates and next
- Jul 2026 to Jan 2027