West Wing cladding survey for City of London goes to Arc Height Safety
- City of London Corporation
- London
- Direct
- 28 June 2025 to 30 August 2025
The City of London Corporation hired Arc Height Safety for a rope access inspection of the West Wing cladding. A structural engineer surveyed the cladding alongside the inspection, after training from Arc Height Safety. The firm also covered the risk assessments and method statements and wrote up a report of what it found.
The corporation awarded the work directly. The £43,074 contract started in June 2025 and was due to end in August 2025.
- What
- Rope access and high-rise cleaning
- Supplier
- Arc Height Safety
- Value
- £43,074
- How it was bought
- Direct
- Dates and next
- Jun 2025 to Aug 2025