Total FM for three Co-op Academies Trust schools goes to Dalkia
- Co-op Academies Trust, run by The Co-operative Academy of Manchester
- North West
- Open procedure, 4 bids
- 1 September 2026 to 31 August 2029
Co-op Academies Trust awarded Dalkia £1.1m to manage facilities at three of its schools, more than three and a half times its £300,000 estimate.
The schools are Co-op Academy Nightingale, Co-op Academy Woodlands and Co-op Academy New Islington, two in Leeds and one in Manchester. Dalkia looks after cleaning, security and caretaking, as well as heating and ventilation, electrical and mechanical systems, planned maintenance and grounds.
The Co-operative Academy of Manchester ran the open tender for the trust, with quality counting for 70% of the score and price for 30%. Four bids came in. Dalkia was chosen in July 2026, and the contract can run to August 2031 with two one-year extensions.
Contract ends August 2029
- What
- Total and integrated facilities management
- Supplier
- Dalkia
- Value
- £1.12m
- How it was bought
- Open procedure
- 4 bids
- Dates and next
- Sep 2026 to Aug 2029
- Option to Aug 2031