Easiform refurbishment of 17 Cottsway homes goes to Westdale Midlands
- Cottsway Housing Association
- South East
- Open
- 4 May 2026 to 28 August 2026
Cottsway Housing Association hired Westdale Midlands Limited to refurbish 17 Mk3 Laing Easiform homes.
Laing Easiform homes are a non-traditional post-war type, built from concrete cast on site. The job covered treatment to reinforce the structure, crack repairs, and cavity wall and external wall insulation, with the enabling works that went with them. The works were to take no more than 17 weeks.
Westdale Midlands was awarded the job in March 2026 after an open tender, at £561,389 against a tender estimate of £450,000. The works were due to finish in August 2026.
- What
- External and internal wall insulation
- Supplier
- Westdale Midlands Limited
- Value
- £561,389
- How it was bought
- Open
- Dates and next
- May 2026 to Aug 2026