Coventry cycle route and signal works go to Breheny Civil Engineering
- Coventry City Council
- West Midlands
- Below threshold - open competition, 9 bids
- 2 November 2026 to 24 September 2027
Breheny Civil Engineering won Coventry City Council's cycle route works for £1,920,490, little more than half the £3.4m the council had estimated.
The work covers three schemes. At Tile Hill Station and along Westwood Way, existing cycle infrastructure is being brought up to the LTN1/20 standard. At Pickford Green Lane, a junction is getting new traffic signals.
Nine bids came in. Price and quality each counted for half the score. Quality was judged on areas such as traffic management, utility and third-party interfaces, delivery to programme and social value. The award came in July 2026 and the works are due to end in September 2027.
Contract ends September 2027
- What
- Footways, cycleways and path construction
- Supplier
- Breheny Civil Engineering
- Value
- £1.92m
- How it was bought
- Below threshold - open competition
- 9 bids
- Dates and next
- Nov 2026 to Sep 2027