Matrix Networks reinforces the power supply to Coventry's Greenpower Park
- Coventry City Council
- West Midlands
- Direct
- 10 April 2026 to 31 December 2028
Coventry City Council directly awarded Matrix Networks the works to reinforce the power supply to Greenpower Park in October 2025. The existing supply had held back development of the site.
The council owns the freehold of Coventry Airport, leased long term to Coventry Airport Limited. In 2021 the two set up a joint venture to market the airport site, now Greenpower Park, for a battery gigafactory.
The council said the work had to go to Matrix Networks. UK Power Distribution, the independent network operator, owns the connection rights for the route, plus the equipment and reserved capacity needed. The contract is worth £15.8m. The works are due to end in December 2028, with a further year allowed for defects.
Contract ends December 2028
- What
- Electricity network works and connections
- Supplier
- Matrix Networks Limited
- Value
- £15.8m
- How it was bought
- Direct
- Dates and next
- Apr 2026 to Dec 2028
- Option to Dec 2029