CHP maintenance for Coventry University comes from Bosch Thermotechnology
- Coventry University
- West Midlands
- Below threshold - without competition
- 3 September 2026 to 31 July 2027
Coventry University is paying Bosch Thermotechnology £67,624 to look after the Bosch combined heat and power (CHP) modules across the university's sites.
The work is preventative. The firm replaces parts that wear out, inspects the modules, checks that they work and services them on a schedule. The university may order corrective repairs separately when they are needed.
The university awarded the contract directly, without a competition. It runs from September 2026 to July 2027.
Contract ends July 2027
- What
- CHP and energy centre maintenance
- 2 of 2 lots awarded
- Buyer
- Coventry University
- Supplier
- Bosch Thermotechnology
- Value
- £67,624
- Across 2 lots
- How it was bought
- Below threshold - without competition
- Dates and next
- Sep 2026 to Jul 2027