ACEDA wins IT cabling work at CPI's research and development facility
- Centre for Process Innovation
- North East
- Open, 6 bids
- 20 February 2026 to 19 February 2029
Centre for Process Innovation (CPI) hired ACEDA Limited, a small business, to provide IT cabling and connections across its research and development facility.
The facility has numerous laboratories, and CPI asked for a contractor who had worked in multi-tenanted buildings. Complex locations counted for 40% of the score, price 30%, methodology 20% and the help desk 10%.
The £300,000 contract was awarded in February 2026 after an open tender that drew six bids. It runs for three years, with two optional one-year extensions that could take it to February 2031.
Contract ends February 2029
- What
- Structured cabling
- Supplier
- ACEDA Limited
- Value
- £300,000
- How it was bought
- Open
- 6 bids
- Dates and next
- Feb 2026 to Feb 2029
- Option to Feb 2031