Clean steam generator for CPI's NIBF1 pilot plant comes from BMM Weston
- Centre for Process Innovation
- North East
- Direct
- 1 April 2026 to 31 March 2029
The Centre for Process Innovation bought an electric clean steam generator from BMM Weston Limited for its National Industrial Biotechnology Facility (NIBF1). The pilot plant houses bioreactors ranging from 10L to 750L. Steam from the generator sterilises equipment in Steam In Place (SIP) cycles and also provides heating.
The generator had to produce more than 175 kg/hr of steam at 3 barg, around the clock, from an electrical supply of no more than 200 amps. It also had to fit in the main plant room without a dedicated boiler house.
The centre awarded the £55,425 contract directly in March 2026, and it runs to March 2029.
Contract ends March 2029
- What
- Industrial and process mechanical services
- 2 of 2 lots awarded
- Supplier
- BMM Weston Limited
- Value
- £55,425
- Across 2 lots
- How it was bought
- Direct
- Dates and next
- Apr 2026 to Mar 2029