Roof edge protection for three CPI buildings goes to James Ingleford
- Centre for Process Innovation
- North East
- Open
- 2 April 2026 to 1 April 2028
The Centre for Process Innovation (CPI) chose James Ingleford Scaffolding Ltd to supply permanent roof edge protection for its buildings.
The work starts with the Coxon, Neville Hamlin and Nigel Perry buildings, and could extend to other CPI sites.
Delivery method and price each counted for 30% of the score. Experience and capability, and health, safety and environmental management, counted for 20% each. The £75,000 contract was awarded in April 2026 after an open tender. It runs for two years, with an option to extend it to March 2029.
Contract ends April 2028
- What
- Height safety, fall arrest and facade access equipment
- Supplier
- James Ingleford Scaffolding Ltd
- Value
- £75,000
- How it was bought
- Open
- Dates and next
- Apr 2026 to Apr 2028
- Option to Mar 2029