Jackson Civil Engineering repairs Gate 4 at Bedford Road Sluice for Defra
- Department for Environment, Food and Rural Affairs
- West Midlands
- Call-off from a framework agreement
- 16 March 2026 to 24 April 2026
The Department for Environment, Food and Rural Affairs ordered repairs to Gate 4 at Bedford Road Sluice from Jackson Civil Engineering.
The sluice is a flood defence asset, and the job was a one-off repair to bring the gate back into working order. The department placed the order as a call-off under AOMR lot 1.
The £77,469 contract ran from March 2026 and was due to end in April 2026.
- What
- Flood defence and flood alleviation works
- Supplier
- Jackson Civil Engineering
- Value
- £77,469
- How it was bought
- Call-off from a framework agreement
- Dates and next
- Mar 2026 to Apr 2026