Local Plan growth and flood advice for Derbyshire Dales comes from Arcadis
- Derbyshire Dales District Council
- East Midlands
- Call-off
- 12 May 2025 to 11 May 2026
Derbyshire Dales District Council hired Arcadis to test whether the housing its Local Plan needs could realistically be built in a sustainable way.
Arcadis was to find sustainable options for where communities in the district could grow up to 2045, to help meet the housing targets the Government had revised. It also gathered traffic and transport evidence for the emerging Derbyshire Dales Local Plan. A Level 2 Strategic Flood Risk Assessment covered the High Sensitive Catchment. It tested how potential development sites, taken together, could affect peak flows on watercourses and the timing and length of flooding.
The council ordered the work through Lot 1 of Homes England's Development and Regeneration Technical Services Framework 2023-2027. The £109,331 contract ran from May 2025 and was due to end in May 2026, with an option for a second year.
- What
- Local plan evidence base studies
- Supplier
- Arcadis
- Value
- £109,331
- How it was bought
- Call-off, Development and Regeneration Technical Services Framework
- Dates and next
- May 2025 to May 2026