SS Richard Montgomery mast removal support for DfT came from PA Consulting
- Department for Transport
- South East
- Call-off from a framework agreement
- 27 January 2025 to 30 June 2025
PA Consulting advised the Department for Transport (DfT) on its project to remove the masts from the wreck of the SS Richard Montgomery. The support covered technical analysis and project advice to help the department manage the removal.
The department ordered the support under a framework agreement. The £375,000 contract started in January 2025 and was due to end in June 2025.
- What
- Marine engineering and naval architecture
- Supplier
- PA Consulting
- Value
- £375,000
- How it was bought
- Call-off from a framework agreement
- Dates and next
- Jan 2025 to Jun 2025