Sinewave Electrical renews Bridport Community Hospital's mains panel board
- Dorset HealthCare University NHS Foundation Trust
- South West
- Limited
- 1 April 2026 to 31 July 2026
Dorset HealthCare University NHS Foundation Trust hired Sinewave Electrical Contractors Ltd to replace the mains electrical panel board at Bridport Community Hospital.
It was a life cycle replacement of the existing board. Sinewave was to remove the old equipment, fit a new electrical distribution system, then test and commission it so the hospital kept a safe power supply.
The trust awarded the £131,599 contract without an open tender. The work was due to run from April to July 2026.
- What
- HV and LV distribution, switchgear and substations
- Value
- £131,599
- How it was bought
- Limited
- Dates and next
- Apr 2026 to Jul 2026