Sinewave Electrical renews the mains panel board at St Leonards Hospital
- Dorset HealthCare University NHS Foundation Trust
- South West
- Below threshold - limited competition
- 1 September 2026 to 31 October 2026
Dorset HealthCare University NHS Foundation Trust hired Sinewave Electrical Contractors to replace the mains electrical panel board at St Leonards Hospital.
The board served the hospital and also the wheelchair centre. Its replacement was part of the trust's backlog of life cycle works.
The trust chose the firm after a limited competition. The £158,874 contract ran from September 2026 and was due to end in October 2026.
- What
- HV and LV distribution, switchgear and substations
- Value
- £158,874
- How it was bought
- Below threshold - limited competition
- Dates and next
- Sep 2026 to Oct 2026