Mitie runs hard facilities management across the Driver and Vehicle Licensing Agency's Swansea estate, replacing services the DVLA had under a 20-year PFI contract.
The estate spans three sites at Morriston, Swansea Vale and Fforestfach. Morriston, the main site, covers 26 acres with seven main buildings and a data centre. The service runs 24 hours a day, all year, for a workforce of around 6,200. The DVLA requires Mitie to use two named suppliers: Schneider Electric to maintain the building management system and CDS for CCTV and access control.
The order came through a further competition under Lot 2c of Crown Commercial Service's Facilities Management & Workplace Services framework (RM6232). The first award notice gave £57.6m for five years from April 2025. A later notice gave £81.7m for the full term to March 2032, both one-year extensions included.
Contract ends March 2032
- What
- Hard FM and multi-trade building maintenance
- Supplier
- Mitie
- Value
- £81.7m
- How it was bought
- Call-off, FM and Workplace Services
- Dates and next
- Apr 2025 to Mar 2032