Asbestos management across the DWP estate goes to Lucion
- Department for Work and Pensions
- Open procedure (above threshold), 11 bids
- 22 May 2025 to 30 September 2028
Lucion won the Department for Work and Pensions' (DWP) UK-wide asbestos management contract for £6.1m, well below the department's £10.24m estimate.
A single consultant looks after asbestos across the department's whole estate, though removal itself is excluded. Lucion carries out surveys, among them UKAS-accredited management surveys, and tests the air after removal work. It also runs a web-based asbestos register and checks removal work done by other contractors.
Eleven bids came in to the open tender. The contract started in May 2025 and is due to end in September 2028.
Contract ends September 2028
- What
- Asbestos management and consultancy
- Supplier
- Lucion
- Value
- £6.1m
- How it was bought
- Open procedure (above threshold)
- 11 bids
- Dates and next
- May 2025 to Sep 2028