Ottery St Mary weir rebuild goes to Bridge Civil Engineering
- East Devon District Council
- South West
- Below threshold - open competition, 2 bids
- 10 November 2026 to 21 October 2027
East Devon District Council (EDDC) is paying Bridge Civil Engineering Limited £144,261 to replace the weir that feeds the Mill Leat near Ottery St Mary. That is nearly one and a half times the council's £100,000 estimate.
The council takes water for the leat from the River Otter at the Head Weir, controlled by the weir at the leat's top end. As that structure has worn, water has been getting round the crest, leaving the river too low for the Head Weir fish pass and eel pass to work. The contractor will remove the weir, build a replacement, dredge the leat and get the environmental permits.
Two bids came in through an open tender, with price worth 80% of the score and quality 20%. Bridge Civil Engineering won in October 2026, and the contract runs to October 2027.
Contract ends October 2027
- What
- Watercourse, culvert and ditch works
- Supplier
- Bridge Civil Engineering Limited
- Value
- £144,261
- How it was bought
- Below threshold - open competition
- 2 bids
- Dates and next
- Nov 2026 to Oct 2027
- Option to Jun 2027