Evoenergy adds ground and car port solar at East Lindsey's Hub
- East Lindsey District Council
- East Midlands
- Below threshold - open competition, 9 bids
- 22 June 2026 to 4 September 2026
East Lindsey District Council hired Evoenergy to add ground-mounted solar panels and solar car ports at The Hub, its headquarters in Horncastle.
The Hub also hosts a Boston College campus, and its roof already carried a 26kW solar system. The council wanted to generate much more of its own electricity there. The new panels were planned for land facing Mareham Road that is hard to develop and over parking in the southern car park. Evoenergy, a small business, was to design the system as well as install and commission it.
Nine bids came in through an open tender. The £320,000 contract gave Evoenergy the site from June 2026, with completion due in September 2026.
- What
- Solar PV and battery storage
- Supplier
- Evoenergy Limited
- Value
- £320,000
- How it was bought
- Below threshold - open competition
- 9 bids
- Dates and next
- Jun 2026 to Sep 2026