Meridian Leisure Centre pool floor gets new hydraulics from Wrightfield
- East Lindsey District Council
- East Midlands
- Direct
- 15 December 2025 to 19 December 2025
East Lindsey District Council hired Wrightfield Limited to replace the hydraulics of the movable pool floor at Meridian Leisure Centre in Louth.
Inspection visits had found a defect in the floor of the main 25m pool, and the hydraulics needed urgent replacement. The job called for an underwater diving support team. The control panel was replaced too, because its closed-protocol system tied it to the firm that first installed it.
The council awarded the £58,200 contract directly. It was due to run in December 2025.
- What
- Swimming pool plant and pool maintenance
- Supplier
- Wrightfield Limited
- Value
- £58,200
- How it was bought
- Direct
- Dates and next
- Dec 2025 to Dec 2025