Geo Houlton part-refurbishes Pollington-Balne Primary School's kitchen
- East Riding of Yorkshire Council
- Yorkshire and the Humber
- Other -
- 20 July 2026 to 31 August 2026
East Riding of Yorkshire Council hired Geo Houlton & Sons Ltd to refurbish part of the kitchen at Pollington-Balne Primary School.
The school's catering appliances were taken out and set aside, and the ones kept were refitted alongside the odd new item of equipment and ventilation. The job also took in hygienic wall cladding, vinyl flooring and a part WC refurbishment.
The £111,171 contract ran from July 2026 and was due to end in August 2026.
- What
- Laboratory and specialist room refurbishment
- Supplier
- Geo Houlton & Sons Ltd
- Value
- £111,171
- How it was bought
- Other -
- Dates and next
- Jul 2026 to Aug 2026