Vectec maintains East of England Ambulance Service fuel pumps and tanks
- East of England Ambulance Service NHS Trust
- East of England
- Open
- 1 March 2026 to 28 February 2029
East of England Ambulance Service NHS Trust hired Vectec to look after the fuel pumps and fuel storage tanks on its estate.
The work mixes planned servicing with repairs when faults arise. It also covers the trust's AdBlue IBC containers and plastic tanks. The trust's estates department calls off jobs as and when it needs them.
The £100,000 contract followed an open tender. It runs to February 2029, with two optional extensions of up to a year each that could take it to February 2031.
Contract ends February 2029
- What
- Depot fuel storage and dispensing equipment
- Supplier
- Vectec Ltd
- Value
- £100,000
- How it was bought
- Open
- Dates and next
- Mar 2026 to Feb 2029
- Option to Feb 2031