AtkinsRéalis checks Blaydon Quarry landfill gas for the Environment Agency
- Environment Agency
- North East
- Call-off
- 3 August 2026 to 31 August 2027
The Environment Agency hired AtkinsRéalis to check landfill gas each month at Blaydon Quarry in Gateshead. The agency needs the readings to show that gas from the site is not polluting the environment or harming people's health.
The work covers 92 boreholes along the southern edge of the site, with monthly reports and an annual summary.
The agency ordered the work through ESPO's 664_25 Consultancy Services framework, under lot 8(h). The £63,233 contract was awarded in July 2026 and runs to August 2027, with an option of up to 12 more months.
Contract ends August 2027
- What
- Emissions, landfill gas and greenhouse gas monitoring
- Buyer
- Environment Agency
- Supplier
- AtkinsRéalis
- Value
- £63,233
- How it was bought
- Call-off, ESPO
- Dates and next
- Aug 2026 to Aug 2027