CCTV and culvert inspections for the Environment Agency go to Breheny
- Environment Agency
- West Midlands
- Call-off from a framework agreement
- 1 October 2026 to 31 March 2027
The Environment Agency is paying Breheny Civil Engineering to carry out CCTV and culvert inspections. The agency placed the work as a call-off from a framework agreement.
Breheny took the £127,172 order in September 2026. The inspections are due to be completed by March 2027, when the contract is set to end.
Contract ends March 2027
- What
- Bridge and structures inspection, assessment and design
- Buyer
- Environment Agency
- Supplier
- Breheny Civil Engineering
- Value
- £127,172
- How it was bought
- Call-off from a framework agreement
- Dates and next
- Oct 2026 to Mar 2027