Coney Gut Reservoir MIOS work for the Environment Agency goes to Kier
- Environment Agency
- South West
- Call-off from a framework agreement
The Environment Agency ordered work from Kier on MIOS improvements at Coney Gut Reservoir.
The improvements are safety measures, meant to keep the reservoir in line with reservoir safety law. The project covers structural repairs, civil engineering and commissioning of the improved works.
The agency placed the order through a framework in May 2026, and it is estimated at £49,067.
- What
- Reservoir and dam works
- Buyer
- Environment Agency
- Supplier
- Kier
- Value
- £49,067
- How it was bought
- Call-off from a framework agreement
- Dates and next
- 14 May 2026