JBA Bentley replaces the Crane tidal gates for the Environment Agency
- Environment Agency
- East of England
- Call-off
- 19 February 2026 to 19 February 2027
The Environment Agency hired JBA Bentley Ltd to replace the Crane tidal gates.
The job is flood defence work, taking out the existing gate structures and fitting new tidal gates. The agency ordered it through lot 2 of its Asset Operation, Maintenance and Response Framework. The £535,091 contract started in February 2026 and is due to end in February 2027.
Contract ends February 2027
- What
- Flood defence and flood alleviation works
- Buyer
- Environment Agency
- Supplier
- JBA Bentley Ltd
- Value
- £535,091
- How it was bought
- Call-off, Asset Operation, Maintenance and Response Framework
- Dates and next
- Feb 2026 to Feb 2027