Derbyshire desilting for the Environment Agency goes to Jackson Civil
- Environment Agency
- East Midlands
- Call-off
- 16 June 2026 to 30 September 2026
The Environment Agency hired Jackson Civil Engineering to clear silt from Derbyshire brooks and drains so that water could flow more freely.
The watercourses included Harrington Drain and Repton, Golden and Hogshaw brooks.
The agency ordered the work through lot 1 of its Asset Operation, Maintenance and Response Framework. The £232,907 contract started in June 2026 and was due to end in September 2026.
- What
- Watercourse, culvert and ditch works
- Buyer
- Environment Agency
- Supplier
- Jackson Civil Engineering
- Value
- £232,907
- How it was bought
- Call-off, Asset Operation, Maintenance and Response Framework
- Dates and next
- Jun 2026 to Sep 2026