Helpston Remediation Project supervision for the EA goes to Jacobs
- Environment Agency
- East of England
- Call-off from a framework agreement
- 5 May 2026 to 31 March 2029
The Environment Agency hired Jacobs to act as ECC Supervisor and provide the ECoW for its Helpston Remediation Project. Through these roles the agency keeps technical oversight of the construction work. The roles also cover checks on environmental standards and a watch on the site's ecology.
The £459,799 call-off was awarded in May 2026 and runs to March 2029.
Contract ends March 2029
- What
- Clerk of works and site supervision
- Buyer
- Environment Agency
- Supplier
- Jacobs
- Value
- £459,799
- How it was bought
- Call-off from a framework agreement
- Dates and next