Hockwold and Wissey Sluice design support comes from Jacobs
- Environment Agency
- East of England
- Call-off from a framework agreement
- 1 May 2026 to 22 August 2028
The Environment Agency hired Jacobs to give construction design support for Hockwold and Wissey Sluice, a flood risk engineering job in East Anglia.
The support covers the sluice's hydro-mechanical structures, with the firm overseeing the engineering and advising on design.
The agency ordered the work as a call-off from a framework agreement. The £148,779 contract runs from May 2026 to August 2028.
Contract ends August 2028
- What
- Flood risk, drainage and coastal engineering
- Buyer
- Environment Agency
- Supplier
- Jacobs
- Value
- £148,779
- How it was bought
- Call-off from a framework agreement
- Dates and next
- May 2026 to Aug 2028